September Progress Report
 

A1139 Frank Perkins Parkway

Completion of drainage / ducting / widening works to southbound carriageway following diversion of EDF high voltage cable.
Kerbing completed to verges and centre reserve and asphalt base layers laid in preparation for surfacing layers to be completed over forthcoming weekend closures.

A15 Paston Parkway

Widening and surfacing operations completed.
75% of road marking and studs installed – not completed due to heavy rain during road closure on Sunday 22 August.

A15 Parnwell Way

Carriageway surfacing completed over weekend closure of 10-13 September.

Roundabout

50% final surfacing laid to circulatory carriageway.
Block paving to centre island approximately 25% complete.

Eye Road

Widening completed to northbound verge, drainage, ducting and kerbing installed
New splitter island constructed.
New kerbing installed to southbound verge.
Surfacing completed up to underside of new surface course

Road Lighting:

Ducting complete, approx 75% columns erected. Lanterns installed on approximately 25% of columns.

Traffic Signals:

Sockets for traffic signal poles 90% complete. Contractor for installation has commenced fabrication works in site compound.

 

 