September Progress Report

All speed cushions now installed.
Kerb realignment between Eastern Avenue and Lombardy Drive approximately 75% complete including junction remodelling of Eastern Avenue, Poplar Avenue and Lombardy Drive.
Junction remodelling of Furze Ride 75% complete.
Widening works to Eastern Gateway Feature approximately 50% complete.
Installation of new road lighting columns is 90% complete, installation of new lanterns and connection by EDF approximately 50% complete.
Traffic sign installation has commenced, approximately  50% complete.